The work of our Ara Damansara Project and the associated buildings and infrastructure has been progressing on schedule. This series of photographs were taken around the first week of June 2013 where significant progress in both Jazz Residences and G Residences is evident.


Top view of Jazz Residences highlights the main structure of Boulevard Shops has been completed with a few levels of the Residences already being constructed on top of the shops.


Jazz Residences - 6 levels of the Residences and Boulevard Shops have been constructed so far.


Construction of the lifestyle mall below G Residences has progressed to 4 levels.


The construction of the LRT track and station next to G Residences are also showing good progress.


Station 2 of Kelana Jaya Line extension is taking shape. This station is situated close to G Residences.